Waste Incineration Facility
 
 
Project Name Municipal Waste Incineration Facility
Project Aim
Waste Incineration System:
- Alternative solution for Landfill-related issues
- Improvement of living condition with cleaner environment
Capacity 1000 ton/day (250 ton/day ¡¿ 4 units)
Contract Plan Turn-key: Design & Construction
Construction Period From contract to within 36 months
 
 
(1) Reception Hall
   
 
 
(2) Bag Filter
   
 
 
(3) Stack
 
  Incineration Solid-Waste Facility
  ¨ç Construction & Operating Cost Down
 
  • Quantity of Machinery reduced
  • High Efficiency Machinery
  • Energy Saving System
  • Low Machinery maintenance
  ¨è Maintenance Effectiveness
 
  • Machinery designed, arranged, and secured for repair effectiveness
  • Simplification of Facilities
  • Secure Conversion of System
  ¨é Neighborhood Residents
 
  • Environmental pollution is far below Malaysia¡¯s acceptable standards
  • Prevents diffusion of dust into atmosphere
  ¨ê Safety, confidence, and smoothness of operation of fully automated system
  ¨ë Compliance of Equipment
 
  • International standard: Civil, Electrical, Mechanical, & Architectural
 
 
 
 
 
 
 
 
 
Construction Record
 
Facility Name
Capacity
( ton/day )
Start Finish Remark
Pyung-Chon, An-Yang Gun 150 1984 1986 Design &
Construction
Kowang-Myung City 200 ¡¯96.03 ¡¯98.11 ¡¨
An-San City 400 ¡¯97.11 ¡¯01.04 ¡¨
Bun-dang, Sung-Nam City 600 ¡¯94.12 ¡¯98.03 ¡¨
Gang-Nam, Seoul 900 ¡¯96.09 ¡¯00.11 ¡¨
Yang-Chon, Seoul 550 ¡¯92.12 ¡¯96.02 ¡¨
   
Design Record
 
Client Name Project Name Capacity ( ton/day )
An-Yang City Basic & Detail Design for Living Waste Incineration Facility, An-Yang City 200
Korea Water Resources
Corporation
Basic & Detail Design for Living Waste Incineration Facility, An-San City 300
Sung-Nam City Basic & Detail Design for Living Waste Incineration Facility, Sung-Nam City 600
Dong-Duchon City Feasibility Study & Basic Plan for Incineration Facility, Dong-Duchon City 100
Dong-Duchon City Feasibility Study & Basic Design for Landfill Facility, Dong-Duchon City 50
Ga- Pyung Gun Basic & Detail Design for Incineration Facility, Ga- Pyung Gun 20
Yong-In City Basic Design for Incineration Facility, Yong-In City 100
Seoul City Supervision for Incineration Facility, Mok-Dong 550
Jegu City Supervision for Incineration Facility, San-Nam & San-Buk 300
Yang-Pyung Gun Supervision for Incineration Facility, Yang-Pyung 50
 
 
Exhaust Allowance Value: International Law
 
Air pollution of Kinds Unit Exhaust Allowance Value Design Basis Value
SOx ppm 300(12) below 30 below
HCl ppm 50(12) below 20 below
NH3 ppm 100 below 50 below
NOx ppm 200 below 75 below
CS2 ppm 30 below 10 below
CO ppm 600(12) below 20 below
HCHO ppm 20 below 7 below
F ppm 3 below 1.5 below
H2S ppm 15 below 7 below
Hg mg/Sm3 5 below 0.05 below
Cd mg/Sm3 1 below 0.05 below
As ppm 3 below 0.02 below
Pb ppm 5 below 1.5 below
Cr mg/Sm3 1 below 0.3 below
Cu mg/Sm3 10 below 2 below
Zn mg/Sm3 30 below 0 below
Ni mg/Sm3 20 below 3 below
Smoke Degree 2 below 0
Dioxin ngTEQ/Nm3 0.5 below 0.1 below
Cl ppm 60(12) below 20 below
HCN ppm 10 below 4 below
Br ppm 5 below 1.5 below
Benzene ppm 50 below 25 below
Phenol ppm 10 below 4 below
Odor Degree 2 below 1 below
Dust mg/Sm3 80(12) below 10 below
Cr mg/Sm3 0.5 below 0.5 below
  International Standard
Standard Oxygen Concentration (O2-12%)
 
 
Section Korea
(Kor. Won :W)
U.S.A
(Dollars : $)
Malaysia (RM) Remark
1. Design Cost
  1) Basic Design
  2) Detail Design
 
3,520,000,000
4,480,000,000
 
2,940,685.044
3,742,690.056
 
11,000,000
14,000,000
 
2.20 %
2.80 %
Total 8,000,000,000 6,683,375.100 25,000,000 5.00 %
2. Construction Cost
  2.1) Mechanical Facility
   - Pretreatment
   - Incineration
   - Combustion gas Treatment
   - Electric Generation
   - Wastewater Treatment
   - Pipe, Duct
   - Air Conditioning
 
 
2,272,000,000
33,600,000,000
12,800,800,000
3,200,000,000
3,200,000,000
4,800,000,000
9,600,000,000
 
 
1,898,078.528
28,070,175.420
10,693,400.160
2,673,350.040
2,673,350.040
4,010,025.060
8,020,050.120
 
 
7,100,000
105,000,000
40,000,000
10,000,000
10,000,000
15,000,000
30,000,000
 
 
1.42 %
21.00 %
8.00 %
2.00 %
2.00 %
3.00 %
6.00 %
Total 69,472,000,000 58,038,428.370 217,100,000 43.42 %
  2.2) Electric Facility
  2.3) Machinery Facility
  2.4) Engineering Works
  2.5) Construction
  2.6) Landscape Architecture
  2.7) Test Operation & Education
  2.8) Management
11,200,000,000
4,800,000,000
19,200,000,000
32,000,000,000
800,000,000
3,200,000,000
4,928,000,000
9,356,725.140
4,010,025.060
16,040,100.240
26,733,500.400
668,337.510
2,673,350.040
4,116,959.062
35,000,000
15,000,000
60,000,000
100,000,000
2,500,000
10,000,000
15,400,000
7.00 %
3.00 %
12.00 %
20.00 %
0.50 %
2.00 %
3.08 %
Total 76,128,000,000 63,598,997.450 237,900,000 47.58 %
3. Supervision Cost 6,400,000,000 5,346,700.080 20,000,000 4.00 %
Grand Total 160,000,000,000 133,667,502.00 500,000,000 100.00 %
  Optional: Pretreatment Facility
1 RM = W 320.00 (Kor Won)
1 USD = W 1,197.00 (Kor Won)
Go with the exchange rate fluctuation
 
 
   